DO Terminale Hejre Crude Stabilization Project

https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-4.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-5.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-6.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-7.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-8.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-2.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-3.jpg

Project: DO Terminale Hejre Crude Stabilization Project

Title:

Description:

DO Terminale Hejre Crude Stabilization Project

https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-4-540x540.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-5-540x540.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-6-540x540.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-7-540x540.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-8-540x540.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-540x540.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-2-540x540.jpg
https://www.solesi.it/wp-content/uploads/2017/07/2500x1663-3-540x540.jpg

Job description

EARTHWORKS:
Excavation in all process areas, for foundations, trenches, pipe lines, culverts.
Backfill in all process areas, for realization of LPG mound, Big Ramp, Embankment outside the refinery.

FOUNDATION AND CONCRETE STRUCTURES:
Realization of all the foundation and structures in all process areas, 3 precast pipe rack, 2 racks cast in place, 2 buildings, 4 culverts, manholes valve boxes and drain channels for underground pipelines, concrete works on jetty area, and reinforced concrete foundations on piles.

UNDERGROUND SYSTEMS:
Realization of new sewer system, with FPI pipes; new fire water system with SARPLAST pipes; new drainage system with carbon steel pipes and FPI pipes. Realization of manholes, valve boxes and drain channels for underground pipelines. Electrical & instrumental cable trenches.

ROADS AND PAVINGS:
Reconditioning of existing roads, construction of new roads, construction of concrete pavings in process areas, walkways and coloured concrete on top of the trenches in paved areas.

CLIENT: DONG OIL PIPE A/S
PLACE: Fredericia, Denmark
START OF THE WORK: 04/2013
END OF THE WORK: 08/2016
WORK AMOUNT: € 32.000.00
MAN HOURS: 415.000
REINFORCING STEEL: 1.200.000 Kg


Sede legale

Via Stentinello, 9 int. 13
96100 Siracusa
Tel.: 0931/751411
Fax: 0931/756944
Email: solesi@solesi.it

Sede commerciale

Via Carlo De Angeli, 3
20141 Milano Tel.: 02/6694125
Fax: 02/6694145
Email: solesi.milano@solesi.it

Branch estere

Belgium Branch - Brussels
Denmark Branch - Roskilde
France Branch - Lyon
Poland Branch - Poznan
Slovakia Branch - Bratislava

Gruppo irem

Via Stentinello, 9
96100 Siracusa
Tel.: 0931/787011
Fax: 0931/756875
Email: irem@iremspa.it